Apply for net metering
with APEPDCL.
By the EdgeGrid energy team · Updated 23 Nov 2026
You can apply on the DISCOM's site, at Mee Seva or on the national rooftop portal, and there is no fee up to 5 kW. APEPDCL checks feasibility, the net-metering agreement follows within four months, and if APEPDCL raises nothing within two weeks the agreement is treated as in force.
We never ask for OTP, bank details or fees.
No fee up to 5 kW. The agreement is treated as in force if APEPDCL raises nothing in two weeks.
Source: APERC rooftop solar net and gross metering rules, as amended in December 2025
step by step
how do I apply for net metering?
Apply online on APEPDCL's site, at a Mee Seva centre or on the national rooftop portal with your service number. APEPDCL checks whether the local network can take your system. After installation it inspects the system, fits the net meter and signs the net-metering agreement before switch-on.
- 1
Apply
On APEPDCL's site, at Mee Seva or on the national rooftop portal, with your service number.
- 2
Feasibility
APEPDCL checks whether the local transformer and lines can take your system.
- 3
Install
An empanelled vendor installs the system.
- 4
Agreement
within 4 monthswhere it often stallsSubmit the net-metering agreement within four months of feasibility.
- 5
Net meter and switch-on
APEPDCL inspects, fits the net meter and switches the system on.
Source: APERC rooftop solar net and gross metering rules, as amended in December 2025
fees
how much does it cost to apply?
Nothing for systems up to 5 kW, which covers almost every home. Larger systems pay a one-time application fee: ₹1,000 from 5 to 100 kW, ₹10,000 from 100 to 1,000 kW and ₹25,000 per MW above that. The fees are set by APERC and are the same across Andhra Pradesh.
| system size | application fee |
|---|---|
| Up to 5 kW | Nil |
| 5 to 100 kW | ₹1,000 |
| 100 to 1,000 kW | ₹10,000 |
| Above 1 MW | ₹25,000 per MW |
- application fee
- Nil
- application fee
- ₹1,000
- application fee
- ₹10,000
- application fee
- ₹25,000 per MW
Source: APERC rooftop solar net and gross metering rules, as amended in December 2025
the agreement
what is the net-metering agreement?
It is the agreement between you and APEPDCL that sets how your imports and exports are measured and settled. Submit it within four months of the feasibility approval. If APEPDCL raises no objection within two weeks of receiving it, the agreement is treated as in force.
Source: APERC rooftop solar net and gross metering rules, as amended in December 2025
after switch-on
what changes on my bill after switch-on?
Your bill starts showing import, export and net units. For LT homes, exports offset imports, and you pay for net units at the normal slab rates plus fixed and customer charges. Units left over are carried forward and settled at the feed-in tariff, or can be shared with other consumers.
read a net-meter bill · earn more from your extra solar units
guides
more on PM Surya Ghar in AP
questions people ask
Is net metering available in Andhra Pradesh?+
Yes. APEPDCL, APCPDCL and APSPDCL all offer net metering for rooftop solar under APERC's rules.
How much does it cost to apply for net metering?+
Nothing up to 5 kW. Above that, ₹1,000 up to 100 kW, ₹10,000 up to 1,000 kW and ₹25,000 per MW beyond.
Where is the net-metering agreement?+
APEPDCL provides it after feasibility. Your vendor usually helps submit it. Keep a signed copy.
planning rooftop solar? ask before you pay.
Send your question on WhatsApp. A person replies with the AP steps that apply to you, and what to check before you sign.