Panels are up, but
no net meter yet.
By the EdgeGrid energy team · Updated 23 Nov 2026
The net meter usually waits on one of three things: the net-metering agreement, APEPDCL's inspection, or a meter to fit. Check the portal status to see which. Once you submit the agreement, APEPDCL has two weeks to raise objections; if it raises none, the agreement is treated as in force.
We never ask for OTP, bank details or fees.
If APEPDCL raises nothing within two weeks of your agreement, it is treated as in force.
Source: APERC rooftop solar net and gross metering rules, as amended in December 2025
where it waits
why hasn't the net meter been fitted?
After installation, three things must happen: the net-metering agreement is submitted, APEPDCL inspects the system, and the net meter is fitted. A delay at any one holds the switch-on. The portal status usually shows which step is pending, and whether it sits with you, the vendor or APEPDCL.
- 1
Agreement submitted
within 4 months of feasibilityOften handled by the vendor. Check it was actually filed.
- 2
APEPDCL reviews
2 weeksNo objection in two weeks means the agreement is treated as in force.
- 3
Inspection
where it often stallsAPEPDCL checks the installation.
- 4
Net meter fitted
Then the system is switched on and the subsidy claim can start.
Source: APERC rooftop solar net and gross metering rules, as amended in December 2025
push it along
how do I push it along?
Ask the vendor for proof the agreement was submitted and the date. If it's with APEPDCL, call 1912, note the complaint number, and write to your section office citing the date you submitted the agreement. Keep copies of everything.
meanwhile
can I use the panels in the meantime?
Not on the grid. A grid-connected system should stay off until APEPDCL switches it on with the net meter, for safety and so that exports are recorded. Switching on early can mean exports aren't counted and can cause problems at inspection.
the subsidy
does the delay hold up my subsidy?
Yes. The subsidy claim starts only after the system is switched on and inspected, so a net-meter delay holds the subsidy too. Once it's fitted, check your bank details on the portal so the claim isn't delayed a second time.
questions people ask
How do I check the net meter reading?+
Net meters cycle through screens. Note the import kWh and the export kWh separately, with the date.
Who do I contact if the net meter is late?+
Ask your vendor for the agreement submission date, then call APEPDCL on 1912 and write to your section office.
How long does the net meter take?+
APEPDCL has two weeks to object to your agreement; then inspection and meter fitting follow. Delays usually sit at one step, which the portal shows.
planning rooftop solar? ask before you pay.
Send your question on WhatsApp. A person replies with the AP steps that apply to you, and what to check before you sign.